Project Status
-
On November 18th, 2006 PIC started a
major step related to ERM, the kick-off meeting of design phase
had already taken place. The day to day activities were being
performed until the completion of the design phase on March 10th,
2007.
-
The 26th of March, 2007 represents a
historical occasion in PIC’s ERM project, PIC Board of Directors
have approved the ERM policy and guidelines.
-
On June 2nd, 2007 PIC started the
kick-off meeting of the implementation phase. During this phase
PIC is implementing the processes and procedure which had been
designed during the design phase. In addition, analyzing the
designing risk management software (Powersim) to meet PIC
requirements.
The completion of the project is expected on the end of December, 2007.
|